I&B Ministry
utilises only 30% of funds
souce:http://www.indiantelevision.com/headlines/y2k11/dec/dec150.php |
Concerned
over the 'unsatisfactory performance' of the Information and Broadcasting
Ministry in spending just over 30 per cent of its allocation in the first
four months of the Eleventh Plan, a Parliamentary Committee has asked the
Ministry to analyse the reasons for under utilisation of outlay
scheme/sector-wise.
The Standing Committee on Communications and Information Technology
dealing with the budgetary demands of the I&B Ministry in a recent report
asked the Ministry to "gear up its monitoring mechanism" to ensure that
the allocated funds are fully utilised and all the on-going schemes may be
strictly monitored to keep pace with the expenditure. The Committee has
also sought a report on the specific steps taken by the Ministry in this
regard.
It noted that the overall outlay for 2011-12 had been increased by Rs
255.8 million over the Budgetary Allocation for 2010-11, which works out
to insignificant increase of 0.97 per cent.
For the Eleventh Plan (2007-12), the
Planning Commission had approved total outlay of Rs 54.39 billion. During
a Mid Term appraisal, the outlay was enhanced to Rs 63.11 billion due to
additional outlay for "High and Lower Power Transmitters for Jammu and
Kashmir Border Areas" and "Commonwealth Games 2010 and Related Programmes".
But the Committee noted that the actual expenditure during the first four
years of the Eleventh Plan was Rs 19.17 billion (Information Sector Rs
2.55 billion, Film Sector Rs 1.98 billion and Broadcasting Sector Rs 14.64
billion), which is just 30.38 per cent of the total Budgetary allocation.
The Committee noted it had expressed serious concern over inability of the
Ministry to fully utilise the outlay in its Sixth Report on Demands for
Grants (2010-11), and had pointed out that under-utilisation of funds is a
perennial problem with the Ministry, which is an indicator of its poor
budgeting mechanism and failure of monitoring mechanism to review the
implementation of various schemes/projects.
In spite of that, the Committee noted that under-utilisation still
persists under different schemes/projects in all three sectors of the
Ministry. Besides inability of the Ministry to fully utilise the outlay,
delay in approval of important schemes of the Ministry, as discussed in
the subsequent part of the report, are areas of concern. The Committee,
therefore, impress upon the Ministry to take steps to make the
implementation mechanism more effective.
Referring to tardy implementation of
schemes, the Committee said that this "clearly indicates that there are
serious problems in the whole planning process which is not conducive for
the overall functioning of the Ministry."
The Committee desired that the Ministry should work out a more streamlined
approval system so that the situation of non-clearance of the schemes does
not persist. The Committee recommended that the Ministry should take
corrective measures so that the situation of non-clearance of schemes does
not get repeated during the Twelfth Plan.
According to the Ministry, it had formulated 86 schemes at the beginning
of the Eleventh Plan. However, the total number of schemes was reduced to
65 at the time of Zero Based Budgeting exercise undertaken by the Planning
Commission in May 2007.
During examination of the previous year's Demands for Grants (2010-11),
the Committee had noted that out of total 38 new schemes, 13 schemes were
awaiting approval and out of 28 on-going schemes, approval for two schemes
was pending. Thus in total 15 schemes were pending clearance/approval.
Having observed that delay in approval of the schemes was one of the
factors responsible for under-utilisation of outlay, the Committee in the
Sixth Report on Demands for Grants (2010-11) had asked the Ministry to
work out a more streamlined approval system.
In spite of that, four important schemes of the Ministry, which include
Global Film School, Setting up of a National Centre of Excellence for
Animation, Gaming and Special Effects, the National Film Heritage Mission
under the Film Sector and the International Channel under the Broadcasting
Sector were still awaiting approval/clearance even when Annual Plan
2011-12 was in the last year of the Eleventh Plan.
The Committee disapproved the way projects are being planned by the
Ministry. All the schemes were formulated at the beginning of the Eleventh
Plan and in the process four precious years were lost.
|||||| Thank you for your interest.||||||
|